| Financial
                      Control 
                         
                Client’s must be able make decisions with
                confidence and that requires all the pertinent
                information to be available at the earliest
                possible time.    We hold weekly meetings
                      with our client and the designer and
                      provide minutes recording any issues
                      discussed, all instructions received from
                      the designer as agreed resolutions to
                      issues discussed, any costs implications
                      for the instructions and an estimated
                      value (with a fixed price established for
                      the item as soon as
                      possible).   
                The minutes also include any issues relating to
                safety, environmental or the local authority
                that have an impact on the
                works. 
                 
                See link to weekly
                minutes
                proforma.   
                Every progress claim states the percentage of
                the original contract sum claimed separate from
                any additional costs agreed or
                estimated.    
                All progress claims show the sum due and the
                revised completion cost.
                      
                    Cash flow statements are
                      prepared and made available to client’s
                      for presentation to their
                      funder.   |